MONDAY - ANDONI 

This Monday we continue to work hard on standard elements. We have to finish all the elements before you have to build the die. The most difficult element to do in my opinion are the punches and the positioners, because they are the elements that have more geometries. The punches and positioners are like this















After drawing them, we decided to insert them into to continue designing the die, and these days we are working harder because the delivery of the die is next week.



TUESDAY - Alain Pacheco

The first hour, Gaizka explained new parameters and new things for the CATIA die.


First, he explained the GEOMETRY ADAPTOR and who we can use.  After that, he explained how we can paste the publication in another part and then he does an example.


In the third hour, we started doing the GEOMETRY ADAPT, the piece Body, the punches and the sketches, All this we finished at 12:00. 

At 12.15 we got it the punches in the die downstair, with the BodyResta to do the holes to passed it the punches.





Wednesday (ANDONI)

On Wednesday at first hour, we have had class with Julen. We did a piece with CATIA, but if we wanted we could progress in the die. We did this for two hours, and then we went to the playtime

Coming back from the playtime, we had class with Nagore, in theory we had to take some measures with the tridimensional, but in the end, we could follow doing the die. So I was making pieces in CATIA.

After we had class with class with Iranzu and we worked as a team to do ACE & HAZE company.


THURSDAY- OIER ZABALA


On Thursday first we have had class with Gaizka, and first of all, we divided the work and we start
working, after 45 minutes Gaizka explained how to do the punches and how to join it.
After the first brake, we should have class with Iranzu but as we are late with the die
we continued with de die, but first, we finished the work that Iranzu sends for this Thursday. 

The last 2 hours we also spend joining the die, and we speak to put overtime some afternoon after
working in the factory, to have finished the die to 22nd November, 1 week earlier of the delivery.


FRIDAY - IKER LÓPEZ
Even though Friday should have started with Iranzu's subject and finished with Nagore's one, we worked on the main project the whole day. We are a bit short of time, so now the much part of the class time is used to continue working on the design of the die. The main project must be handed in the 29th of November.




This Friday we finished adding the stamps/punches we had left to its corresponding plate. And apart from that, we also revised and updated all the standardised and constructive elements we had already done through the last weeks to be sure there's no problem with them.